Question
25 men can complete a piece of work in 30 days. ‘x’
men started the work and after 24 days 60 more men joined them so that whole work was finished in the desired time. Find the value of ‘x’Solution
Total work = 25 × 30 = 750 units According to question; 24 × x + 6 × (x + 60) = 750 Or, 24x + 6x + 360 = 750 Or, 30x = 390 Or, x = 13
What is the name of India’s newly inducted mobile counter-drone system by DRDO?
- What is the total transaction value recorded via UPI in FY24 according to Worldline?
India’s first vulture conservation portal was launched in which state?
When was the Border Security Force (BSF) established?
India signed Terms of Reference (ToR) to begin FTA negotiations with the Eurasian Economic Union (EAEU). What was the combined GDP of the EAEU region in...
How many new AI-related jobs could India generate in the next five years, as per NITI Aayog’s Roadmap for Job Creation in the AI Economy?
- What was India's Current Account Deficit (CAD) as a percentage of GDP in Q3 FY25?
The Government of India is planning to nearly double the corpus of the IndiaAI Mission over five years. What will be the new outlay?
Indian Renewable Energy Development Agency Ltd. (IREDA) celebrated its 38th Foundation Day on March 11, 2024. What is IREDA's role in India?
Which city was highlighted as the world's most polluted in January 2025?