Question
A alone can do a piece of work in 10 days and B alone in
15 days. In how many days will they finish the work together?Solution
ATQ, A's 1-day work = 1/10 B's 1-day work = 1/15 Together in 1 day = 1/10 + 1/15 LCM of 10 and 15 = 30 1/10 = 3/30, 1/15 = 2/30 Total = (3 + 2)/30 = 5/30 = 1/6 So time = 6 days
What is the horticultural term used to describe peaches that do not have surface fuzz on the fruit skin?
Which carnation variety is known for its long vase life and resistance to calyx splitting?
It is the practice of smoking under trees to induce early flowering in mango., The popular practice is said to be
What are the physical indicators of a healthy seedling?
In Rose cultivation, "bent neck" is a physiological disorder caused by:
How is asexual propagation defined?
Which among the following chrysanthemum varieties is not considered suitable for making garlands?
Which organization is responsible for agricultural research in India?
What is the chemical nature of Peat?
HQ of International Society for Horticulture Science (ISHS) is at ________