Question
'A' and 'B' can complete a piece of work in 10 days, 'B'
and 'C' can complete the work in 16 days, and 'A' and 'C' can complete the work in 20 days. Find the time taken by 'B' to complete 50% of the work. (Answer should be rounded off to the nearest integer)Solution
ATQ, Let the total work be 80 units (LCM of 10, 16, and 20). Combined efficiency of 'A' and 'B' =(80/10) = 8 units/day Combined efficiency of 'B' and 'C' = (80/16) =5 units/day Combined efficiency of 'A' and 'C' =(80/20) = 4 units/day So, combined efficiency of 'A', 'B', and 'C' = [(8+5+4)/2] = 8.5 units/day And, efficiency of 'B' = 8.5 - 4 = 4.5 units/day Therefore, required time ={(0.5×80)/4.5} = 9 days
How much area in percentage is covered under storage in rural go down?
Calculate water requirement of a plant using following details :
Pan evaporation-6 mm
Row to row spacing-10 m
Plant to plant...
Which among the following is an egg laying mammal?
Bt term was discovered by ………………………… while working on ………..disease of silkworm.
...'Sugar baby' is a cultivar of -
The most reactive among the halogens is-
Who is the father of organic farming?
The ratio of average depth of water stored in root zone soil depth during irrigation to the water diverted from the reservoir is known as
T.S.S of Tomato puree should be (ºBrix)