      Question

      If 3/5 of the work is done by 35 workers in 6 days, then

      how many more workers would be required to complete the remaining work in next 2 days?
      A 20 workers Correct Answer Incorrect Answer
      B 25 workers Correct Answer Incorrect Answer
      C 15 workers Correct Answer Incorrect Answer
      D 35 workers Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the extra workers required be β€˜x’. According to question, (35 Γ— 6)/ (3/5) = {(35 + x) Γ— 2}/ (2/5) (210 x 5)/ 3 = {(35 + x) x 2 x 5} / 2 70 = 35 + x, x = 35 So, the number of extra workers required = 35