    (x) men can do some work in 42 days. If 10 more men

    added then the work would have been completed in 30 days, then in how many days (x+45) men can do the same work?
    A 25 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 12 days Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    let the┬а Ratio of days is = 42 : 30 = 7 : 5 then Ratio of men will be┬а = 5 : 7 2 units = 10 1 unit = 5 5 units = 5 x 5 = 25 Therefore, (x) = 25 (x + 45) = 70 men Therefore, Number of days taken by (x + 45) men will be┬а = 25 x (42/70) = 15 days┬а