Question
(x) men can do some work in 42 days. If 10 more men added then the work would have been completed in 30 days, then in how many days (x+45) men can do the same work?
More Time and work Questions
- A and B together can complete a piece of work in 48 days while B and C together can complete the same work in 58 days. All of three together can complete 8...
- Amit manages to reach 25% of a sales goal in 6 days, whereas Geeta can achieve 40% of the same goal within the same timeframe. How long would it take for b...
- 4 girls can do work in 8 days, 3 boys can do the same work in 9 days, 7 men in 2 days, and 5 women in 4 days. Who is the least efficient?
- 'P' completes a work in 18 days whereas 'Q' completes the work in 54 days. Both of them started the work together, but 'Q' left the work 6 days before the ...
- A alone can complete 60% of a work in 24 days while B takes 20 days more than A to complete it. If B and C together can complete the work in 35 days, then ...
- 15 people can paint a house in 5 days using 15 paintbrushes. In how many days can 10 people paint the same house using p paintbrushes?
- A alone can do a piece work in 15 days and the time taken by A alone is 50% more than the time taken by B. They started work together alternatively startin...
- Pipe ‘X’ can fill a tank 15 minutes faster than Pipe ‘Y’. If both are opened together, they can fill the tank in 18 minutes. If 180 litres of water passes ...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 40 days, respectively. If they started the work together and worked on it for 6 days, then find the time ...
- 40 men can complete a piece of work in 48 days. ‘x’ men started the work and after 30 days 56 more men joined them so that whole work was finished in the d...