šŸ“¢ Too many exams? Don’t know which one suits you best? Book Your Free Expert šŸ‘‰ call Now!


    Question

    (x) men can do some work in 42 days. If 10 more men

    added then the work would have been completed in 30 days, then in how many days (x+45) men can do the same work?
    A 25 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 12 days Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    let theĀ  Ratio of days is = 42 : 30 = 7 : 5 then Ratio of men will beĀ  = 5 : 7 2 units = 10 1 unit = 5 5 units = 5 x 5 = 25 Therefore, (x) = 25 (x + 45) = 70 men Therefore, Number of days taken by (x + 45) men will beĀ  = 25 x (42/70) = 15 daysĀ 

    Practice Next
    ask-question