Question

    X men can complete the piece of work in 36 days and (X +

    30) men can complete the same work in 15 days less than that of days taken by X men. Find the value of X. 
    A 34 Correct Answer Incorrect Answer
    B 42 Correct Answer Incorrect Answer
    C 55 Correct Answer Incorrect Answer
    D 44 Correct Answer Incorrect Answer
    E 63 Correct Answer Incorrect Answer

    Solution

    According to question, => X × 36 = (X + 30) × 21 => 36X = 21X + 630 => 15X = 630 => X = 42