      Question

      X men can complete the piece of work in 36 days and (X +

      30) men can complete the same work in 15 days less than that of days taken by X men. Find the value of X. 
      A 34 Correct Answer Incorrect Answer
      B 42 Correct Answer Incorrect Answer
      C 55 Correct Answer Incorrect Answer
      D 44 Correct Answer Incorrect Answer
      E 63 Correct Answer Incorrect Answer

      Solution

      According to question, => X Ă— 36 = (X + 30) Ă— 21 => 36X = 21X + 630 => 15X = 630 => X = 42