Question
The day efficiency of Rajeev is equal to the one-day
efficiency of Divya and Vivek together. Divya is 25% more efficient than Vivek and starts with 20% more of his efficiency with Vivek and works for x days, after that Divya left the work and remaining work will be completed by Vivek and Sanjay together in (x + 10) days. If ratio of work done by Divya and Vivek together to work done by Vivek and Sanjay is 5:7 and efficiency of Sanjay is 50% less than Vivek. Then Rajeev and Sanjay complete work together in how many days?Solution
Ratio of efficiency of Divya: Vivek = 125:100 = 5: 4 Efficiency of Sanjay = 4 × (1/2) = 2 units/day According to question, (5 × (120/100) + 4) x / (4 + 2) (x + 10) = 5/7 10x / (6x + 60) = 5/7 70x – 30x = 300 x = 7.5days Total work = (10 × 7.5) + (6 × 17.5) = 75+105 = 180 ATQ-Rajeev efficiency = (Divya + Vivek) = 9 units/day Sanjay and Rajeev efficiency = (2 + 9) = 11 units/day (Sanjay + Rajeev) = 180/11 days
A and B together can do a work in 5 days. If A can alone do the same work in 15 days, then in how many days B alone will do the same work?
A and B can complete a job together in 30 days; B and C can complete the same job together in 25 days, while C and A can complete the same job together ...
Sufficient food-supply was arranged to last for 30 days for 250 soldiers. If 50 soldiers did not attend the camp, for how many extra days will the food-...
‘A’ is 80% more efficient than ‘B’. ‘A’ and ‘B’ work together for 5 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C�...
Shivam and Harish can do a job alone in 90 days and 120 days respectively. Both work together and earn Rs. 5,250. Find Shivam’s earnings.
Suppose Y individuals can complete a task in (Y - 28) days, and (Y + 12) individuals can finish the same task in (Y - 32) days, what is the number of da...
- 40 women working 10 hours a day take 12 days to complete a project. How many women working for 7 hours a day are needed to complete twice the given project...
‘A’ and ‘B’ can do a piece of work in 15 days and 20 days, respectively. They started working together but ‘A’ left after 3 days. Find the t...
3 men, 4 women and 5 boys can do a piece of work in 15 days, 20 days and 25 days respectively. For first 3 days 3 men and 2 women work together and for ...
Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the rem...