πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    ⚑ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug ⚑ Enroll Now

    Question

    A’ and β€˜B’ alone can do a certain work in 20 days

    and 30 days, respectively. Both started the work together but after β€˜x’ days β€˜A’ left the work and the rest work was completed by B alone in β€˜2x’ days. Find the total time taken to complete the whole work in this way.
    A 110/3days Correct Answer Incorrect Answer
    B 120/7days Correct Answer Incorrect Answer
    C 121/7days Correct Answer Incorrect Answer
    D 154/3days Correct Answer Incorrect Answer
    E none of these Correct Answer Incorrect Answer

    Solution

    Total work = 60 units (LCM of 20 and 30) Efficiency of β€˜A’ = 60/20 = 3 units/day Efficiency of β€˜B’ = 60/30 = 2 units/day According to the question, β€˜A’ worked for β€˜x’ days and β€˜B’ worked for β€˜2x days. Therefore, 3x + 2 Γ— 2x = 120 Or 3x + 4x = 60 Or x = 60/7days total time taken to complete the whole work = 2Γ—60/7=120/7days

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call