Let efficiency of P = p and efficiency of Q = q p = 160% of q => p: q = 8: 5 Let time required by P and Q together to finish this job be “t”. (p + q) ×t = W => 13x × t = W …. (1) ATQ- p × (t + 30) = W => 8x × (t + 30) = W … (2) By solving above two equations we get t = 48 13x × 48 = 5x × T => T = 124.8 days