P is 60% more efficient than Q. P takes 30 more days to
finish a work as compared to the number of days taken by P and Q together to finish the same work. Find the time taken by Q to finish the same work alone.Solution
Let efficiency of P = p and efficiency of Q = q p = 160% of q => p: q = 8: 5 Let time required by P and Q together to finish this job be “t”. (p + q) ×t = W => 13x × t = W …. (1) ATQ- p × (t + 30) = W => 8x × (t + 30) = W … (2) By solving above two equations we get t = 48 13x × 48 = 5x × T => T = 124.8 days
What is the significance of Zeenat’s translocation to Odisha’s Similipal Tiger Reserve?
CPI inflation in India (August 2025) was recorded at:
On which date World Red Cross Day is celebrated annually?
In April 2026, the Government of India approved a Rs. 30 billion currency swap facility for Maldives under which framework?
Who was given a one-year extension as Director of the Intelligence Bureau till June 2026?
Which of the following is the name of the joint exercise conducted between the Indian and Vietnam Coast Guards?
How many personnel are participating in AJEYA WARRIOR-25 from both Indian and UK armies?
Keki Mistry joined Housing Development Finance Corporation (HDFC Ltd) in which year?
What was the Centre’s fiscal deficit as a percentage of the full-year target in the first half (H1) of FY26?
The government has directed which body to create a coordinated response mechanism for AI-related threats?