Let, total work = (LCM of 11, 20, and 55) = 220 efficiency of P = 20 units Efficiency of Q = 11 units Efficiency of R = 4 units Work done by P and Q in first day = 20 + 11 = 31 Work done by P and R in second day = 20 + 4 = 24 Total work done by P, Q, and R in 2 days = 31 + 24 = 55 55-unit work done by all three in = 2 days 220-unit work done by all thee in = [2/55] × 220 = 8 days.
Who has laid the foundation stone of “Experience Spirituality at Chitrakoot Ghat” project in Chitrakoot, Madhya Pradesh?
Where is India's first vulture breeding center located?
Which city was recently declared as the tourism capital of the Country by the government of Nepal ?
Recently, where was the 148th Inter-Parliamentary Union meeting held?
India signed a defence cooperation agreement in 2025 with which country, particularly in the areas of missiles and MANPADS?
Why was the Simon Commission, established in 1927, boycotted by the Indian National Congress?
ADB has provided how much loan to the government of India for financing the construction of the 82-kilometer Delhi-Meerut Regional Rapid Transit System ...
Which financial institution recently launched the first sustainability-linked payables finance program in Asia for BASF in China?