      Question

      40 women working 10 hours a day take 12 days to complete a

      project. How many women working for 7 hours a day are needed to complete twice the given project in 15 days if they work at 25% higher efficiency?
      A 25 Correct Answer Incorrect Answer
      B 89 Correct Answer Incorrect Answer
      C 64 Correct Answer Incorrect Answer
      D 120 Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the total work be 'W' units and the efficiency of each woman be 'E' units/hour.

      Let the number of women required be 'M'.

      ATQ:

      Image