      Suraj is one third as good as workman as Pankaj and

      together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish the work is
      A 190 days Correct Answer Incorrect Answer
      B 144 days Correct Answer Incorrect Answer
      C 249 days Correct Answer Incorrect Answer
      D 48 days Correct Answer Incorrect Answer

      Solution

      Ratio of efficiency of Pankaj & Suraj = 3:1 & they do a job in 36 days so let total work = (3+1)`xx` 36 = 144 units Hence Suraj alone will finish this job in = 144/1 = 144 days