Question
4 men and 6 women together or 8 men can complete a piece
of work in 20 days. 6 men and 6 women will complete the same work inSolution
(4m + 6w) = 8m 6w = 4m 3w = 2m Now, 6m + 6w = 6m + 4m = 10m 8 m×20 = (6m + 6w)×T =10m×T T = 16 days