Question
A, B and C can complete the whole work in 20 days. A
starts the work and works for ‘x’ days while B and C complete the remaining 3/5 of the work in 15 days, then find the value of ‘x’.Solution
Time required by B and C to complete the work = 5 × 15/3 = 25 days Time taken by A, B and C = 20 days Total units of work = 100 units B and C one day work = 4 units A, B and C one day work = 5 units A’s one day work = 5 – 4 = 1 units Units of work done by A = 2 × 100/5 = 40 units Required value of x = 40/1 = 40 days
The output of the circuit below is _______
Maximum Power transfer occurs when the_____
Fill in the correct option for 28 blank space.
What is the backbone of MIS?
The latency of a network isÂ
A circuit has five branches with four nodes including reference node , then the number of linearly independent mesh equation would be_______
Which of the following statement is TRUE related to Alpha Beta pruning algorithm?
What is the primary purpose of the UNION ALL operator in SQL?
In object-oriented programming, when defining an interface method, which of the following statements is true regarding method parameters?
What is the shortcut for 'Undo' in most software?