Time required by B and C to complete the work = 5 × 15/3 = 25 days Time taken by A, B and C = 20 days Total units of work = 100 units B and C one day work = 4 units A, B and C one day work = 5 units A’s one day work = 5 – 4 = 1 units Units of work done by A = 2 × 100/5 = 40 units Required value of x = 40/1 = 40 days
The SATH-E (Sustainable Action for Transforming Human Capital - Education) initiative's role model states include?
Which bank has become the first to officially introduce the Mahila Samman Savings Certificate (MSSC) scheme?
Indian origin Laxman Narasimhan has assumed the role of CEO and will join the board of directors of which of the following Companies?
Which of the following keyboard shortcuts is used to lock your PC in a Windows 10 operating system?
The famous Sardar Sarovar dam has been built on which of the following rivers?
One of the distinct features of the peninsular plateau is the black soil arca known as _________.
As per Economic Survey 2021-22, the ______ sector contributed the most to the GDP of India during the year.
‘Dakar Declaration’ is a joint statement related to
The subject of the Study of Macro Economics is based on which principle?
Which writ is issued when the court finds that there is unlawful arrest of a person?