      Question

      A, B and C can complete the whole work in 20 days. A

      starts the work and works for ‘x’ days while B and C complete the remaining 3/5 of the work in 15 days, then find the value of ‘x’.
      A 25 days Correct Answer Incorrect Answer
      B 30 days Correct Answer Incorrect Answer
      C 53 days Correct Answer Incorrect Answer
      D 40 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Time required by B and C to complete the work = 5 × 15/3 = 25 days Time taken by A, B and C = 20 days Total units of work = 100 units B and C one day work = 4 units A, B and C one day work = 5 units A’s one day work = 5 – 4 = 1 units Units of work done by A = 2 × 100/5 = 40 units Required value of x = 40/1 = 40 days