Start learning 50% faster. Sign in nowEfficiency Ratio = A : B = 125 : 100 = 5 : 4 Days Ratio = A : B = 4 : 5 B takes 30 days to complete a piece of work. => 5’s = 30 => 1’s = 6 => 6’s = 24 So A can complete the work in 24 days. Total units of work = 120 (LCM of 24,30) A = 5 unit B = 4 unit A and B worked for 4 days = 4 × (5+4) = 36 units Remaining work = 120 – 36 = 84 units Hence, A worked alone for = 84/5 days.