Question
Efficiency of A is 25% more than B and B takes 30 days
to complete a piece of work. A started the work alone and then B joined him 4 days before actual completion of the work. For how many days A worked alone?Solution
Efficiency Ratio = A : B = 125 : 100 = 5 : 4 Days Ratio = A : B = 4 : 5 B takes 30 days to complete a piece of work. => 5’s = 30 => 1’s = 6 => 6’s = 24 So A can complete the work in 24 days. Total units of work = 120 (LCM of 24,30) A = 5 unit B = 4 unit A and B worked for 4 days = 4 × (5+4) = 36 units Remaining work = 120 – 36 = 84 units Hence, A worked alone for = 84/5 days.
Which type of payment is the Reserve Bank of India (RBI) not responsible for regulating directly?
Ullambana is the festival of which of the following religion?Â
Who won the Bal Sahitya Puruskar 2019 in Hindi language?
Which State's Chief Minister has been awarded the Bharat Ratna Dr Ambedkar Award for fear free state, in May 2023?Â
In US Open 2022, the player that lost to Carlos Alcaraz is a _______ player.
Which of the following banks is the TV broadcast sponsor for Indian Team In Asian Games?
‘La Liga’ title is associated with _______.
At which session of Congress was the proposal ‘Poorna Swaraj’ passed?
The word 'direct free kick' is related to which of the following sports?
Name the captain of the Indian Men's Hockey Team as of 30th July 2020.