Question
A can do a piece of work in 40 days. A is 25% more
eicient than B. In how many days the work gets completed when both of them work together?Solution
Efficiency of A = 1/40 Efficiency of B = (1/40) × (1/1.25) = 1/50 Time taken by B to complete the work = 50 days Let the total amount of work = 200 units Amount of the work done by A in one day = 200/40 = 5 units Amount of the work done by B in one day = 200/50 = 4 units Time taken by both to complete the work = (200/9) days
‘Aaj se thoda kam’ is awareness campaign to eliminate trans fats by 2022. Which of the following is not part of this?
Shifting cultivation is practiced in which agro-climatic zones
Herbicide atrazine belongs to which category of herbicides?
Seed rate of Pennisetum glaucum L. is
Apna Khet Apna Kaam is the scheme of under MGNREGA which state?
Which bacterium is responsible for denitrification in N2 cycle?
Who is considered the Father of Plant Tissue Culture?
The majority of phytophagous nematodes are?
What is the initial substrate for glycolysis?
What is the primary difference between Theoretical Field Capacity and Effective Field Capacity?