ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    M and N, working in tandem, can successfully attain the

    sales target within a span of 15 days. Now, if N's efficiency is _______ percent less than that of M, what is the duration _______ in days that N, working alone, requires to accomplish the sales target? Which set of values from the options provided will correctly complete the statement to render it accurate? i)┬а 25, 35 ii) 50, 45 ii) 40, 40
    A Only i Correct Answer Incorrect Answer
    B Only ii Correct Answer Incorrect Answer
    C Only i and ii Correct Answer Incorrect Answer
    D only ii and iii Correct Answer Incorrect Answer
    E All i, ii and iii is correct Correct Answer Incorrect Answer

    Solution

    ATQ, Let the efficiency of M be тАШ20mтАЩ units/day For i: Efficiency of N = 20m ├Ч 0.75 = тАШ15mтАЩ units/day Total amount of work = (20m + 15m) ├Ч 15 = тАШ525mтАЩ units Time taken by N alone to complete the whole work = 525m ├╖ 15m = 35 days Therefore, (i) is true. For ii: Efficiency of N = 20m ├Ч 0.50 = тАШ10mтАЩ units/day Total amount of work = (20m + 10m) ├Ч 15 = тАШ450mтАЩ units Time taken by N alone to complete the whole work = 450m ├╖ 10m = 45 days Therefore, (ii) is true. For iii: Efficiency of N = 20m ├Ч 0.60 = тАШ12mтАЩ units/day Total amount of work = (20m + 12m) ├Ч 15 = тАШ480mтАЩ units Time taken by N alone to complete the whole work = 480m ├╖ 12m = 40 days Therefore, (iii) is true.

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question