Question
A man does double the work done by a boy in the same
time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men in 8 days isSolution
work done by man : work done by boy = 2: 1 let work done by a man in 1 day = 2 units let work done by a boy in 1 day = 1 units work done by 10 men in 8 days = 10 × 2 × 8 = 160 units work done by 3 men and 4 boys in 1 day = 3 × 2 + 4 × 1 = 10 units number of days = 160/10 = 16 days
Ratna variety of Mango isa cross of ?
Live microbial supplements that benefited human health by the microbial balance in the intestine called
Which ministry is responsible for implementing the Agricultural Export Policy in India?
Calculate the seed rate (kg/ha) of wheat, if crop is sown at spacing of 18 cm×3 cm and rest weight of seed is 44 gram
What is the primary symptom of myxomatosis in rabbits?
Among the given crops, which crop has the highest percentage of irrigated area?
The element found on the surface of the moon is:
The hydraulic brakes used in automobiles is a direct application of :
Which layer of the atmosphere is responsible for most of the Earth's weather patterns?
Rapid fall in the activity of metabolic processes especially respiration in crop plants due to decrease in temperature up to 0 to 10oC and m...