      Akhil and Nikhil together can complete a work in 6 days

      while Nikhil alone takes 18 days to complete 60% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.
      A 9 days Correct Answer Incorrect Answer
      B 6 days Correct Answer Incorrect Answer
      C 7 days Correct Answer Incorrect Answer
      D 5 days Correct Answer Incorrect Answer

      Solution

      Time taken by Nikhil to complete the whole work alone = 18/0.60 = 30 days Let the total work = 30 units Efficiency of (Akhil + Nikhil) = 30/6 = 5 units/day Efficiency of Nikhil = 30/30 = 1 units/day Efficiency of Akhil = 5 - 1 = 4 units/day Therefore efficiency of Sachin = 1.25 x 4 = 5 units/day Time taken by Sachin to complete the whole work alone = 30/5 = 6 days