Question

‘X’ and ‘Y’ together can complete a work in 8 days, while ‘Y’ and ‘Z’ together can complete the work in 5 days. If ‘Y’ takes 10 days to complete the work alone then find the approximate time taken by all three together to complete 57.5% of work.

A 3 days
B 7 days
C 9 days
D 5 days
E 6 days