Question
‘X’ and ‘Y’ together can complete a work in 8 days, while ‘Y’ and ‘Z’ together can complete the work in 5 days. If ‘Y’ takes 10 days to complete the work alone then find the approximate time taken by all three together to complete 57.5% of work.
More Time and work Questions
- ‘M’ and ‘N’ can do a piece of work in 9 days and 18 days, respectively. ‘M’ started working alone and was replaced by ‘N’ after 3 days. In how many days ca...
- 'A' and 'D' together can finish a project in 40 days. If 'D' alone can complete 25% of the project in 15 days, then find out how long it takes for 'A' alon...
- ‘P’ can complete 40% of a task in 24 days, while ‘Q’ can complete 25% of the task in 20 days. How long will it take approximately for ‘P’ and ‘Q’ together ...
- P and Q can do a piece of work in 32 and 40 days respectively. They began to work together but P leaves after sometimes and Q completed remaining work in 1...
- A can complete a piece of work in 27 days. He worked for 21 days and then B finished the remaining work in 8 days. In how many days can A and B finish the ...
- A, B, and C can individually complete a task in 20 days, 15 days, and 10 days, respectively. B and C begin the task and work together for 3 days, after whi...
- A builder recruited 60 workers to do a task in 90 days. It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many addition...
- A can copy 70 pages in 20 hours, A and B together can copy 120 pages in 12 hours. Then in how many pages can B copy 10 hours.
- A and B can do a piece of work in 12 days and 18 days, respectively. They start working together, and after 4 days, A leaves the work. How many more days w...
- Working alone, B can complete the work in 20 days. C is twice as efficient as B and A takes 2 days more than it takes C to complete the work. Working toget...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt