Question
Ajay alone can finish 60% of a task in 18 days. Vijay takes
15 days longer than Ajay to complete the entire task. When Vijay and Chirag work together, they can complete the full task in 20 days. How many days will Chirag alone take to finish the same task?Solution
ATQ;
Time taken by 'Ajay' alone to complete the entire work = 18 Ć· 0.6 = 30 days
Time taken by 'Vijay' alone to complete the entire work = 30 + 15 = 45 days
Let the total work = L.C.M of 30, 45 and 20 = 180 units
Then, efficiency of 'Vijay' = (180/45) = 4 units/day
Combined efficiency of 'Vijay' and 'Chirag' = (180/20) = 9 units/day
So, efficiency of 'Chirag' alone = 9 - 4 = 5 units/day
So, time taken by 'Chirag' alone to complete the entire work = (180/5) = 36 days
Lalit Kala Akademi, the National Academy of Art was setup in:Ā
Which of the following is a dance form from the state of Uttarakhand?
Who is the author of the book āThe Glass Palaceā?
Kerala is famous in what form -
The first English factory was set up on the banks of the river ______ in 1651.
Which tennis player won the men's single title of "Australian Open 2025"?
What do you call the drugs that bind to the receptor site and inhibit its natural function?
Which of the following statements about a āunicorn' is/are correct?
1. In the venture capital industry, the term unicorn' refers to any startup...
Which of the following sites of Indus Valley Civilization is located in Punjab (India)?
Who among the following applied European theatrical techniques to Indian Classical dance with folk and tribal dance?