Question
Ajay alone can finish 60% of a task in 18 days. Vijay takes
15 days longer than Ajay to complete the entire task. When Vijay and Chirag work together, they can complete the full task in 20 days. How many days will Chirag alone take to finish the same task?Solution
ATQ;
Time taken by 'Ajay' alone to complete the entire work = 18 ÷ 0.6 = 30 days
Time taken by 'Vijay' alone to complete the entire work = 30 + 15 = 45 days
Let the total work = L.C.M of 30, 45 and 20 = 180 units
Then, efficiency of 'Vijay' = (180/45) = 4 units/day
Combined efficiency of 'Vijay' and 'Chirag' = (180/20) = 9 units/day
So, efficiency of 'Chirag' alone = 9 - 4 = 5 units/day
So, time taken by 'Chirag' alone to complete the entire work = (180/5) = 36 days
If 50 percent of the families in a certain city subscribe to the morning newspaper, 65 percent of the families subscribe to the afternoon newspaper and ...
The 'Special Drawing Right (SDR)' is an international reserve asset created by:
What is the primary theme of India’s Union Budget 2024-25?"
The Mundell-Fleming framework studies (A) _____ , (B) _________ economies in a world with (C) _____ financial markets and (D) _____ capital mobility
Which among the following are the recommendations of the Urjit Patel Committee report on monetary policy?
I. Curtailment of the fiscal deficit.
Under the Bretton wood system, the long-term development assistance was to be provided by
-
IBRD
...
-
If rxy = 0.75, then ryx will be:

When a firm operates with excess capacity