Question
P and Q can finish a job working
together in 24 days. P completes two-thirds of the task in 'd' days, and Q finishes the rest in 'd/4' days. Determine the value of 'd'.Solution
ATQ, Time taken by P to complete the task = d/(2/3) = (3/2)d days Time taken by Q to complete the task = (d/4)/(1/3) = (3d/4) days According to question, 2/3d + 4/3d = 1/24 (2 + 4)/3d = 1/24 2/d = 1/24 d = 2 × 24 = 48
In a certain code language, ‘PREFER’ is coded as ‘KIVUVI’. What is the code for ‘DEFINE’ in that code language?
What is the code for ‘say may’ in the given code language?
What is the code for ‘letters newly’?
In a certain code language, ‘TRIPLE’ is written as ‘SUQJFM’, then how will ‘OPTION’ be written in that language?
If third digit of each number is replaced by 4, then how many numbers will be divisible by 7?
In a certain code language ‘SHINE’ is written as ‘ITIFO’ and ‘PRIVATE’ is written as ‘JSQVFUB’. How is &...
If ‘Earth’ is called as ‘Mars’, ‘Mars’ is called as ‘Venus’, and ‘Venus’ is called as ‘Jupiter’, then, which planet is known as...
In a certain code language, ‘KPURKTG’ is written as ‘LRVVLBH’. How will ‘HQTIKXG’ be written in that language?
In a certain code language, ‘market outlook remains’ is written as ‘xc, sd, kv’, ‘experts over positive remains’ is written as ‘kv, mn, qa...
If white is called blue, blue is called red, red is called yellow, yellow is called green, green is called black, black is called violet and violet is c...