Question
Riya can do a piece of work in 30 days, and Mehul can do
it in 45 days. Find the number of days Kabir will take to complete the job if he is 20% more efficient than Riya and Mehul working together.Solution
Let total amount of work = 90 units (LCM of 30 and 45) Work done by Riya in one day = 90 / 30 = 3 units Work done by Mehul in one day = 90 / 45 = 2 units Combined = 3 + 2 = 5 units Kabir’s efficiency = 1.2 × 5 = 6 units/day Time taken by Kabir = 90 / 6 = 15 days
Which computer part is responsible for storing data permanently, even when the power is turned off?
A car travels a distance of 240 km in 4 hours. If it increases its speed by 20 km/h for the next 3 hours, how much distance will it cover in total?
Anoop has a specific number of ₹10 coins and ₹5 coins. The total number of coins is 37, and the number of ₹10 coins is 13 l...
What is the % increase in the total number of shoes sold by Seller 'C' over the four days compared to the total number sold by Se...
Rajesh spent 30% and 25% of his monthly salary on food and rent, respectively. Of the remaining amount, he gave 20% and 40% to his mother and brother, r...
If a line has direction ratios 2, -1, -2, determine its direction cosines.
Compute P(A∩B), if P(B) = 0.8 and P(AǀB) = 0.35
I). p 2  – 17p + 70 = 0
II). q 2  – 25q + 154 = 0