Riya can do a piece of work in 30 days, and Mehul can do
it in 45 days. Find the number of days Kabir will take to complete the job if he is 20% more efficient than Riya and Mehul working together.Solution
Let total amount of work = 90 units (LCM of 30 and 45) Work done by Riya in one day = 90 / 30 = 3 units Work done by Mehul in one day = 90 / 45 = 2 units Combined = 3 + 2 = 5 units Kabir’s efficiency = 1.2 × 5 = 6 units/day Time taken by Kabir = 90 / 6 = 15 days
In which city the World Bank has launched its first 'Road Safety Project' in South Asia?
What is the primary benefit of the property card issued under the SVAMITVA scheme?
Which of the following was a significant technological focus for the National Institute of Animal Biotechnology (NIAB)?
Which region was categorised as the World’s Most Unequal Region in the World Inequality Report 2022?
Who holds the record for the fastest World Cup hundred by an Indian?
How much is the proposed maritime development fund for which the government will sign agreements?
World Science Day for Peace and Development is observed every year on?
Who has won the singles title of the Indian Wells Masters?
Which eminent Indian astrophysicist received the COSPAR Harrie Massey Award 2024?
Who is the winner of the World Games Athlete of the Year award 2021.