Question
Riya can do a piece of work in 30 days, and Mehul can do
it in 45 days. Find the number of days Kabir will take to complete the job if he is 20% more efficient than Riya and Mehul working together.Solution
Let total amount of work = 90 units (LCM of 30 and 45) Work done by Riya in one day = 90 / 30 = 3 units Work done by Mehul in one day = 90 / 45 = 2 units Combined = 3 + 2 = 5 units Kabir’s efficiency = 1.2 × 5 = 6 units/day Time taken by Kabir = 90 / 6 = 15 days
What does the acronym ULLAS stand for in the context of the ULLAS- Nav Bharat Saaksharta Karyakram scheme?
Share of MSME Gross Value Added (GVA) in All India Gross Domestic Product at current prices (2011-12) for the year 2018-19 was _____ ?
The members of PM-KMY Scheme are required to make a monthly contribution to the Pension Fund between _______ to _________, depending on their age with ...
What is India’s Labour Force Participation Rate (LFPR) for persons aged 15 and above as of October 2025?
According to the 2025 HDR, which of the following countries rank below India in HDI?
What was BASEL Committee on Banking Supervision established?
Which ministry is responsible for implementing the SVAMITVA scheme?
Which initiative helped reduce the misuse of household cylinders for commercial purposes and ensured subsidies reached the intended beneficiaries by dir...
PM Suraksha Bima yojana is an affordable insurance scheme for the poor and underprivileged people in the age group of?
Which state is not amongst the 31 states where Aspirational block program is being implemented?