Question
Amit is five times as efficient as Deepak and twice as efficient as Farhan. If Deepak takes 60 days to finish some work, then find the time taken by Amit and Farhan to do the same work together.
More Time and work Questions
- 50 men can complete a piece of work in 10 days. ‘x’ men started the work and after 5 days 60 more men joined them so that whole work was finished in the de...
- Komal and Seema individually can complete a task in ‘2a’ hours and ‘5a’ hours respectively. If they together can complete half of the work in 5 hours, then...
- A and B together can complete a piece of work in 12 days, while B and C together can complete the same work in 15 days. A and C together can complete the w...
- ‘A’ is 25% less efficient than ‘B’, and ‘C’ is 75% more efficient than ‘B’. All three together complete a task in 32 days. After ‘A’ and ‘B’ work together ...
- ‘A’ alone can do some work in 10 days. ‘B’ and ‘C’ together can do the same work in 4 days. If ‘B’ is half as efficient as ‘A’, then find the time taken by...
- A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men ...
- A alone can complete a work in 20 days and B alone in 30 days. A works alone for 10 days and then B joins him. In how many total days will the work be comp...
- A and B can complete a task together in 18 days, while B alone takes 36 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- Sam and John can complete a piece of work in 8 days and 12 days respectively. They work together but after 2 days, Sam leaves. John finishes the remaining ...
- ‘A’ alone can do some work in 10 days. ‘B’ and ‘C’ together can do the same work in 12 days. If ‘B’ is half as efficient as ‘A’, then find the time taken b...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt