Question
Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to complete the entire task in 9 days?
More Time and work Questions
- 15 people can paint a house in 5 days using 15 paintbrushes. In how many days can 10 people paint the same house using p paintbrushes?
- Ravi and Sunil can complete a task in 12 days and 30 days respectively. Ravi started the task alone. After how many days should Sunil join him so that the ...
- If Neha can complete a work in 40 days by working 5 hours a day, how many hours per day should she work to complete the same work in 25 days?
- E and F can complete a task in 24 days together. E alone can do it in 40 days. Find the time F alone would take.
- Arjun, Binny, and Chiku can collaborate to finish a particular task in 12 days. Additionally, Arjun and Binny working together can complete the task in 15 ...
- 16 men can complete a work in 10 days. 10 men started the same work and left after working for ‘y’ days. The remaining work is completed by 6 men in 15 day...
- 5 men and 10 women can do some work in 3 days. If each man is 150% more efficient than a woman, then find the time taken by 9 men to finish the same work t...
- M and N together complete a work in 10 days, while N alone does it in 16 days. If the efficiency of M to O is in the ratio 5:6, what is the ratio of effici...
- 25 tailors can sew 200 dresses in 40 days by working 5 hours per day. How many tailors are needed to sew the same number of dresses in 25 days by working 8...
- Akhil and Nikhil together can complete a work in 6 days while Nikhil alone takes 18 days to complete 60% of the work. If the efficiency of Sachin is 25% mo...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt