Question
Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to complete the entire task in 9 days?
More Time and work Questions
- A alone can complete a work in 10 days and B alone can complete it in 15 days. They work together for 5 days and then C alone finishes the remaining work i...
- 3 women and 1 girl together can complete a work in 25 days. 2 women and 5 girls can together complete half of the same work in 9 days. Find the time taken ...
- Some Category of workers can complete a decided project in 20 days. However, due to some unpredicted situation, 5 workers were absent. That’s why, the proj...
- Time taken by 'X' and 'Y' to complete a work alone is 72 days and 120 days respectively. Find the time taken by 'X' and 'Y' together to complete 25% of the...
- ‘A’ and ‘B’, alone can complete a work in 25 days and 50 days, respectively. Both of them started the work together but ‘A’ left the work when 2% of the wo...
- Rahul, Sameer, and Dinesh can complete a task in 24 days, 36 days, and 18 days, respectively. They started working together, but Rahul left after 3 days. H...
- Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the sa...
- P can do a work in 20 days, Q in 30 days. They work together, but P leaves 5 days before completion. Find total time.
- A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days...
- 'Amit' can finish a __ percentage of work in 4 days on his own. 'Bishnu' requires 4 days less than 'Amit' to complete the same task individually. Consequen...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt