Question

    A alone can complete 40% of a work in 18 days while B

    takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, then find the time taken by C alone to complete the same work.
    A 30 days Correct Answer Incorrect Answer
    B 36 days Correct Answer Incorrect Answer
    C 24 days Correct Answer Incorrect Answer
    D 42 days Correct Answer Incorrect Answer
    E 21 days Correct Answer Incorrect Answer

    Solution

    Time taken by A alone to complete the entire work = 18/0.4 = 45 days Time taken by B alone to complete the entire work = 45 + 15 = 60 days Let the total work = L.C.M of 45, 60 and 20 = 180 units Then, efficiency of B = (180/60) = 3 units/day Combined efficiency of B and C = (180/20) = 9 units/day So, efficiency of C alone = 9 – 3 = 6 units/day So, time taken by C alone to complete the entire work = (180/6) = 30 days

    Practice Next

    Relevant for Exams: