Question
A alone can complete 50% of a work in 9 days while B
takes 6 days more than A to complete it. If B and C together can complete the work in 12 days, then find the time taken by C alone to complete the same work.Solution
Time taken by A alone to complete the entire work = 9/0.5 = 18 days Time taken by B alone to complete the entire work = 18 + 6 = 24 days Let the total work = L.C.M of 18, 24 and 12 = 72 units Then, efficiency of B = (72/24) = 3 units/day Combined efficiency of B and C = (72/12) = 6 units/day So, efficiency of C alone = 6 – 3 = 3 units/day So, time taken by C alone to complete the entire work = (72/3) = 24 days
How many projects were completed by the person who lives on the floor number 5?
____ is mother-in-law of O.
Four of the following five are alike in a certain way based on the given arrangement and thus form a group. Which is the one that does not belong to tha...
Which of the following statements is/ are true regarding W?
Who is taller than Rakesh but shorter than Bhaskar?
Which of the following does not belong to the group?
- Answer the questions based on the information given below. Eight shelves G, H, I, J, K, L, M and N are there in an almirah but not necessarily in the same ...
A's marks were how much more than that of B?
What is the position of Y with respect to K?
Who among the following live on topmost floor?