Question
A alone can complete 50% of a work in 9 days while B
takes 6 days more than A to complete it. If B and C together can complete the work in 12 days, then find the time taken by C alone to complete the same work.Solution
Time taken by A alone to complete the entire work = 9/0.5 = 18 days Time taken by B alone to complete the entire work = 18 + 6 = 24 days Let the total work = L.C.M of 18, 24 and 12 = 72 units Then, efficiency of B = (72/24) = 3 units/day Combined efficiency of B and C = (72/12) = 6 units/day So, efficiency of C alone = 6 – 3 = 3 units/day So, time taken by C alone to complete the entire work = (72/3) = 24 days
- What does the "H" in the HLOOKUP function of MS Excel stand for?
If a = b in the equation of ellipse x²/a² + y²/b² = 1, then the curve becomes:
The equation of a hyperbola whose conjugate axis equals its transverse axis is:
The average weight of 32 dogs was initially computed to be 45 kg. However, it was later discovered that the weights of two dogs w...
Find the equation if a point P(x, y) is equidistant from A(7, 3) and B(-3, 7).
A car covers the first 40 km of a journey at 60 km/h and the next 60 km at 90 km/h. What is the average speed for the entire journey?
If the speed of a boat in still water is 20 km per hour and the speed of current is 5 km per hour then the time taken by the boat to travel 150 KM with ...
Quantity I: A shopkeeper bought an article for Rs. 3000 and marked its price up by 50%. He then gave two successive discounts of 10% and ‘x’%, makin...
What is the total sales for Product B in all four quarters combined?