Question
A alone can complete 50% of a work in 20 days while B takes 16 days more than A to complete it. If B and C together can complete the work in 24 days, then find the time taken by C alone to complete the same work.
More Time and work Questions
- P alone can finish a piece of work ‘M’ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 7 ti...
- ‘A’ can complete a work in 15 days and is 50% more efficient than ‘B’. ‘A’ and ‘B’ start working together and ‘A’ leaves after 8 days. The rest of the work...
- Ajay and Vijay can finish a task in 9 days working together. Charu, who is twice as efficient as Vijay, can complete the task alone in 18 days. If Ajay and...
- (y+15) men can do a piece of work in (z-30) days. (y-15) men can do the same piece of work in (z+45) days. If (y+25) men can do the same work in (z-45) day...
- 40 men are engaged to dig a 4 km long drainage channel. After working 12 days, only 1/2 of the work is done. Then 8 more men are employed. Find the number ...
- 8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women work...
- Efficiency of a man is 25% more than that of a woman. (n - 10) men working 6 hours a day can complete a task in 18 days, whereas (n - 9) women working 6 ho...
- Billy, Tony and Mike were three workers, employed by a Contractor. They completed the whole work in 20 days. Initially all of them worked together, but the...
- Anand is capable of finishing a task in 36 days when working solo. Akash, being 40% more efficient than Anand, can accomplish tasks quicker. Calculate how ...
- 'A' alone can finish a job in 12 days. If 'A' is twice as efficient as 'B' who is 20% as efficient as 'C', then find the time taken to finish the job if th...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt