Question
A alone can complete 50% of a work in 10 days while B
takes 8 days more than A to complete it. If B and C together can complete the work in 12 days, then find the time taken by C alone to complete the same work.Solution
Time taken by A alone to complete the entire work = 10/0.5 = 20 days Time taken by B alone to complete the entire work = 20 + 10 = 30 days Let the total work = L.C.M of 20, 30 and 12 = 420 units Then, efficiency of B = (420/28) = 15 units/day Combined efficiency of B and C = (420/12) = 35 units/day So, efficiency of C alone = 35 – 15 = 20 units/day So, time taken by C alone to complete the entire work = (420/20) = 21 days
Select the number from among the given options that can replace the question mark (?) in the following series.
2, 13, 29, 55, 96, 157, 243, ? <...
Which of the given figures when placed in the 5th position would continue the series that is established by the first four figures?
After interchanging the given two numbers, what will be the value of the given expression?
20 and 10
10 + 30 – 5 × 20 ÷ 2
Select the option that represents the correct order of the given words as they would appear in an English dictionary.
1. Circulate
2. Circ...
X-Ray : Radiologist :: Skin : ?
Select the option that will replace the question mark (?) in the figure given below to complete the pattern.
Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it appears to be at variance...
Which figure from the options will replace the question mark (?) in the following figure series?
Select the set in which the number are related in the same way as the numbers of the given sets. (NOTE : Operations should be performed on the whole num...
Select the option that is related to the third word in the same way as the second word is related to the first word. (The words must be considered as me...