📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    Ram can do a piece of work in 12 days and Shyam can do

    the same work in 20 days. They both started work together, Ram left 4 days before the completion of the work. Then the total work is completed in how many days?
    A 10days Correct Answer Incorrect Answer
    B 12days Correct Answer Incorrect Answer
    C 15days Correct Answer Incorrect Answer
    D 8days Correct Answer Incorrect Answer

    Solution

    Required Answer = [((20-4) Ă—12)/ (12+20)] + 4 = (16 Ă— 12)/32 + 4 = 10 days

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call