The ratio of time taken by P, Q and R to complete work alone is 6:8:3 respectively. If all three together complete the work in 5 days, then find in how many days P alone will complete two-third of the same work?
Ratio of efficiency of P, Q & R = 4 : 3 : 8 So, let total work = (4x + 3x + 8x) × 5 = 75x unit Required days = 75x × 2/3 × 1/4x = 12.5 days
The President of India is elected indirectly by the electoral college consisting of the elected members of the:
Part Performance of a contract of transfer is mentioned under Section ……… of Transfer of Property Act
According to the Prevention of Money-Laundering Act, 2002 whoever commits the offence of money-laundering shall be punishable with________________
Preventive relief is granted at the discretion of the court by_____________
On an application made to ______________by the company, a company limited by shares or limited by guarantee and having a share capital may, by a special...
What is the full form of FSSAI?
Suit for recovery of possession of immovable property under section 6 of Specific Relief Act can be filed:
Any person aggrieved by an order of the Board made before the commencement of the Securities Laws (Second Amendment) Act, 1999 may prefer an appeal to ...
What is the Bailment of goods as security for payment of a debt or performance of a promise called?
The Board of Directors of a company need approval at the company general meeting for contribution, to bona fide charitable and other funds, exceeding __...