Question
'X' and 'Y' together can complete the work in 16 days.
'Y' alone can complete the work in 24 days. If Z is 50% more efficient than X, find the time taken by 'Z' alone to finish the work.Solution
Let the total work be 240 units Combined efficiency of 'X' and 'Y' = (240/16) = 15 units/day Efficiency of 'Y' alone = (240/24) = 10 units/day Efficiency of 'X' alone = 15 - 10 = 5 units/day Efficiency of 'Z' = 5 X (3/2) = (15/2) units/day Time taken by 'Z' alone to finish the work = 240 ÷ (15/2) = (240 X 2)/15 = 32 days
Which member of honey bee colony produces royal jelly?Â
Breeder seed is the progeny of
Which of the following diseases is caused by a virus and is characterized by the formation of nodules on the skin of cattle?
What is the purpose of mulesing in sheep farming?
Protein content in Soybean is:
Which one of the following statements is incorrect for the management of ‘wilt disease’ in chickpea?
. Opening up of monopoly markets to increase foreign and domestic competition is:
What is Phostoxin?Â
At 50-75 % ASM range (Available soil moisture range)____ soils, form ball and ribbons out between thumb and fore fingers
What is inflation in economics?