Question
'A', 'B' and 'C', alone can do some work in 28 days, 35 days and 70 days, respectively. If they work together for wages of Rs. 6,600, then find the difference between shares of 'B' and 'C'.
More Time and work Questions
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- 'X' and 'Y' can complete a certain job together in 36 days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work al...
- P, Q and R can do some work in 11 days, 20 days and 55 days respectively. In how many days can the work be done, if P gets the assistance of Q and R on alt...
- Raj, Sanjay and Vaibhav can separately finish a work in 20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by San...
- 'B' is 20% more efficient than 'A.' 'A' began working on a task alone and continued for 8 days, after which 'B' took over and completed the remaining work ...
- ‘A’ and ‘B’ can complete a certain work in 10 days and 15 days, respectively. They started working together and worked till completion of the work for whic...
- Four lights blink at intervals of 18 seconds, 24 seconds, 36 seconds, and 48 seconds respectively. How many times will all the lights blink together in 3 h...
- ‘M’ and ‘N’ can do a piece of work in 9 days and 18 days, respectively. ‘M’ started working alone and was replaced by ‘N’ after 3 days. In how many days ca...
- 24 delivery boys can complete a delivery in 15 days. If 12 boys start the same work, and after 12 days, 'd' more boys join the work, completing the remaini...
- ‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.1400, then fin...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt