Question
A builder recruited 60 workers to do a task in 90 days. It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many additional workers need to be hired in order to complete the work on schedule.
More Time and work Questions
- Ajay and Vijay together can paint a piece of furniture in 11 days. Vijay and Chirag together, as well as Ajay and Chirag together, can paint the same piece...
- A can complete a piece of work in 21 days. A starts the work alone. After 9 days, B joins A, and together they complete the remaining work in 5 days. Find ...
- Aman and Rohan can finish a job alone in 12 days and 30 days respectively. Aman began the task alone. After how many days should Rohan join him so that the...
- 40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are nee...
- A, B, and C are three workers who can complete a certain piece of work. A alone can complete the work in 12 days. B alone can complete the same work in 3X ...
- P, Q, and R can do a project individually in 10, 25, and 20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days will ...
- Raman can complete a certain task by himself in 30 days. Both Raman and Rajat worked together to finish this task, earning a combined wage of Rs. 5,850. Ou...
- 25 men can finish a work in 8 days by working 9 hours a day. How many more men are needed to finish the work in 10 days by working 6 hours a day?
- 'P', 'Q', and 'R' can complete a job in 60, 90, and 120 days respectively. They begin together, but 'P' leaves 10 days before the work is done and 'Q' leav...
- A fence is constructed using 900 wooden planks. ‘X’ alone can place 10 planks per minute, while ‘Y’ alone can complete the fence in 100 minutes. ‘Z’, a cur...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt