A builder recruited 60 workers to do a task in 90 days.
It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many additional workers need to be hired in order to complete the work on schedule.Solution
ATQ, Let 'a' more workers joined after 60 days and let total task be 3u units Using (men X days) ÷ task = constant {(60 X 60) /u} = {(60 + a) X 30} ÷ 2u Or, a = 180 Therefore, 180 extra workers are needed so that task gets completed on time.
The Nobel Peace Prize 2017 was won by
Recently a public procurement portal for Micro and Small Enterprises has been launched. The name of the portal is
Priority Sector Lending Certificates (PSLCs) incentivises the seller bank for over-achievement of the PSL targets
Â
16th January was celebrated as 'Opinion Poll Day' or 'Asmitai Dis' in the state of:
BS norms or Bharat Stage norms are emission standards set by government to regulate pollution from vehicles. Currently which stage of BS norms is in pla...
Karnataka government launched the ‘Mathru Purna’ scheme for ___________?Â
Where is the headquarters of the Rubber Board located?
When was the bob Utsav Deposit Scheme launched by Bank of Baroda, and what is the highest interest rate available under this scheme for non-callable dep...
What is the currency of Oman?
 The first life insurance company established in 1818 in India was?