Question
A builder recruited 60 workers to do a task in 90 days.
It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many additional workers need to be hired in order to complete the work on schedule.Solution
ATQ, Let 'a' more workers joined after 60 days and let total task be 3u units Using (men X days) ÷ task = constant {(60 X 60) /u} = {(60 + a) X 30} ÷ 2u Or, a = 180 Therefore, 180 extra workers are needed so that task gets completed on time.
As per Union Budget 2025-26, what is the new cap on Foreign Direct Investment (FDI) in the space sector?
Which of the following is not covered under priority sector?
To raise the quality of education the Prime Minister Shri Narendra Modi has announced a scheme Schools for Rising India (PM SHRI) for which the cabinet ...
Which of the following Statements about NCERT is/are True?
(i) NCERT provides academic and technical support for qualitative improvement of schoo...
Which of the following city of Gujarat become India’s first operational smart city with the development of world-class infrastructure and sustain...
Mahatma Gandhi National Fellowship Programme (MGNF) in collaboration with IIM is providing certificate course in ______ ?
As per the Union Budget 2024-25, how many high-yielding and climate-resilient crop varieties will be released?
What is the allocated amount for the Defence Budget in the Financial Year 2024-25?
Recently which of the following Indian firm has buy the majority of stake in Isreal Haifa Port?
Who has has been named as the managing director of TATA Projects?