A builder recruited 60 workers to do a task in 90 days.
It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many additional workers need to be hired in order to complete the work on schedule.Solution
ATQ, Let 'a' more workers joined after 60 days and let total task be 3u units Using (men X days) ÷ task = constant {(60 X 60) /u} = {(60 + a) X 30} ÷ 2u Or, a = 180 Therefore, 180 extra workers are needed so that task gets completed on time.
Three of the following four letter-cluster pairs are alike in a certain way and thus form a group. Which is the letter-cluster pair that does NOT belong...
Study the following arrangement of two digit numbers and symbols to answer the question given below
       37 43 87 & 32 54 @ % 89 65 44 ...
19 is related to 39 following a certain logic. Following the same logic, 1 is related to 3. To which of the following is 3 related following the same lo...
Two different positions of the same dice are given below. Which is the number on the face opposite the face containing 1?
HFLI is related to OMSP in a certain way based on the English alphabetical order. In the same way, KIOL is related to RPVS. To which of the following is...
A word arrangement machine, when given an input line of words, rearranges them in steps according to the following rules.
INPUT LINE: Trial Toda...
Select the number from the given alternatives that can replace the question mark (?) in the following series. Â
22, 25, 35, 59, 104, ?
In a certain code language, ‘DAYS’ is coded as ‘3917’ and ‘YOLK’ is coded as ‘2496’.What is the code for ‘Y’ in that language?
...After the mid-term examination Rupesh ranked 10th from the top and Rachit ranked 21st from the bottom. If Rachit performed better than Rupesh and six st...
Study the given pattern carefully and select the number that can replace the question mark (?) in it.