A builder recruited 60 workers to do a task in 90 days.
It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many additional workers need to be hired in order to complete the work on schedule.Solution
ATQ, Let 'a' more workers joined after 60 days and let total task be 3u units Using (men X days) ÷ task = constant {(60 X 60) /u} = {(60 + a) X 30} ÷ 2u Or, a = 180 Therefore, 180 extra workers are needed so that task gets completed on time.
What is the projected value of India's retail digital payments by 2030?
What is the base year for the Quick Estimates of IIP (Index of Industrial Production)?
Who was recently honored with the ‘Vishwambhara Dr. C. Narayana Reddy National Literary Award’?
With reference to DINKAR herbicide launched by Dhanuka Agritech, consider the following statements:
1. DINKAR has been developed in collaboration...
Which of the following tiger reserves in Chhattisgarh is NOT integrated into the newly established Guru Ghasidas-Tamor Pingla Tiger Reserve?
What was the growth rate of India's gross GST collections in July 2024 compared to the previous month?
What is the new transaction limit for tax payments via UPI set by the RBI?
After the announcement of Bharat Ratna to former Prime Minister Chaudhary Charan Singh, which political party decided to join the ruling NDA alliance?
What new rule will HFCs (Housing Finance Companies) need to follow starting January 2025 regarding public deposits?
Which of the following is NOT a method for farmers to register for the PM-KISAN scheme?