Question
A and B can do a piece of work in 30 days and 40 days,
respectively. They began the work together but after a certain time, A leaves off and B completed the remaining work in 26 days. After how many days did A leave?Solution
Let, after x days A leave. Let the total work is the 120 units (LCM of 30 and 40) Efficiency of A is 120 / 30 = 4 units The efficiency of B is 120/40 = 3 units So, after x days they both work together. According to the question, (4+3) x x + 26 x 3 = 120 Â 7x + 78 = 120 7x = 42 Â x = 42/7 days =6 days.
Match Column I and Column II and choose the correct match from the given choice
Match Column I and Column II and choose the correct match from the given choices
In the following questions two columns are given. In column-I three sentences are given, each of them consisting of a blank which may or may not be fil...
In the following question, a sentence is divided in to three parts, given in column 1, 2 and 3. Match the statements from column 1 with those in column...
In the following questions two columns are given. In column-I three sentences are given, each of them consisting of a blank which may or may not be fil...
Directions: Match the words in Column A with their meanings in Column B, and choose the correct combination from the options given below:
...BUT
In the following question, two columns are given, containing three phrases each. A phrase from the first column may or may not connect with a phrase fr...