Question
A and B can do a piece of work in 30 days and 40 days,
respectively. They began the work together but after a certain time, A leaves off and B completed the remaining work in 26 days. After how many days did A leave?Solution
Let, after x days A leave. Let the total work is the 120 units (LCM of 30 and 40) Efficiency of A is 120 / 30 = 4 units The efficiency of B is 120/40 = 3 units So, after x days they both work together. According to the question, (4+3) x x + 26 x 3 = 120 7x + 78 = 120 7x = 42 x = 42/7 days =6 days.
Which one of the following statements is true
What is Universal Banking?
Which of the following is not a debt security?
In which year the first Bank of India was established?
Which of the following person is not the Deputy Governor of RBI?
IFSC Code contains how many characters that facilitate fund transfer in any part of the country?
India’s first regional rural bank is ___________
Which of the following statements is true about Debt-Service Ratio?
The new rupee symbol is presented by the Government of India in
Escorts has signed MoU with ________ for tractor financing.