📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    A and B together can complete a work in 10 days, B and C

    together in 12 days and C and A together in 15 days. In how many days can each of them complete the work alone?
    A 40 days Correct Answer Incorrect Answer
    B 28 days Correct Answer Incorrect Answer
    C 52 days Correct Answer Incorrect Answer
    D 33 days Correct Answer Incorrect Answer

    Solution

    Let daily work rates be a, b, c. a + b = 1/10 b + c = 1/12 c + a = 1/15 Add all three: 2(a + b + c) = 1/10 + 1/12 + 1/15 LCM(10,12,15) = 60 1/10 = 6/60, 1/12 = 5/60, 1/15 = 4/60 Sum = 15/60 = 1/4 ⇒ a + b + c = 1/8 Now: a = (a + b + c) − (b + c) = 1/8 − 1/12 = 3/24 − 2/24 = 1/24 ⇒ A alone: 24 days b = (a + b + c) − (a + c) = 1/8 − 1/15 = 15/120 − 8/120 = 7/120 ⇒ B alone: 120/7 days c = (a + b + c) − (a + b) = 1/8 − 1/10 = 5/40 − 4/40 = 1/40 ⇒ C alone: 40 days.

    Practice Next
    ask-question