Question
Ajay alone can complete a work in 50 days. Vijay is four
times as efficient as Ajay. Find the percentage of work completed by Ajay and Vijay together in 10 days.Solution
ATQ,
Let the efficiency of Ajay = x units/day
Total work = 50x units
Efficiency of Vijay = x Γ 4 = 4x units/day
Work done by Ajay and Vijay together in 10 days = (x + 4x) Γ 10 = 50x units
Percentage of work done = (50x / 50x) Γ 100 = 100%
Employing a lawyer to draft and enforce a private contract between parties wishing to solve an externality problem is an example of a(n) ______________cost
What is the slope of the Engel curve for a Giffen good?
In monopolistic competition, long-run equilibrium occurs where price is:
VIF test is done for which of the following?
A firm finds that for the product it produces, its (own) price elasticity of demand is 4. Currently, the firm is selling 1000 units per month at Rs. 5 p...
What do you mean by ‘under conditions of a perfect competition in the product market’?
A Lerner Index of 0 indicates which of the following market conditions?
In which of the following models, price Β is driven down to marginal cost?
If bxy = 0.20 and rxy = 0.50, then byx is equal to: