Question
Ajay alone can complete a work in 50 days. Vijay is four
times as efficient as Ajay. Find the percentage of work completed by Ajay and Vijay together in 10 days.Solution
ATQ,
Let the efficiency of Ajay = x units/day
Total work = 50x units
Efficiency of Vijay = x × 4 = 4x units/day
Work done by Ajay and Vijay together in 10 days = (x + 4x) × 10 = 50x units
Percentage of work done = (50x / 50x) × 100 = 100%
Which of the following should come in the place of question mark ?
BAC EDF HGI ?
...Select the number combination of letters that when placed sequentially in the blanks of the given series will complete the series.
j _ l m _ o _ ...
Select the option that represents the letters that, when placed from left to right in the same sequence in the blanks below, will complete the letter se...
Find the odd word/letters/number pair from the given alternatives.
Select the combination of letters that when sequentially placed in the blanks of the given letter series will complete the series.
u _ v v v _ _ ...
Select the option that represents the letters that when sequentially placed from left to right in the blanks below, will complete the letter series.
...Select the combination of letter that when sequentially placed in the blanks of the given series will complete the series.
A _ _ D E _ B C D _ ...
Select the combination of the letters that when placed sequentially in the blanks of the given letter series will complete the series.
M M H T _ ...
Select the combination of numbers that when placed sequentially in the blanks of the given series will complete the series.
a b _ d _ f g _ i _...
Select the correct combination of the letters that when sequentially placed in the blanks of the given letter series will complete the series.
a ...