      Question

      Ajay alone can complete a work in 50 days. Vijay is four

      times as efficient as Ajay. Find the percentage of work completed by Ajay and Vijay together in 10 days.
      A 43% Correct Answer Incorrect Answer
      B 60% Correct Answer Incorrect Answer
      C 80% Correct Answer Incorrect Answer
      D 100% Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the efficiency of Ajay = x units/day

      Total work = 50x units

      Efficiency of Vijay = x Γ— 4 = 4x units/day

      Work done by Ajay and Vijay together in 10 days = (x + 4x) Γ— 10 = 50x units

      Percentage of work done = (50x / 50x) Γ— 100 = 100%