Question

    A and B together can do a piece of work in 15 days which

    B and C together can do in 20 days. After A has been working at it for 3 days and then by B for 11 days & then C finishes it in 20 days. In how many days B could finish the work?
    A 48 days Correct Answer Incorrect Answer
    B 24 days Correct Answer Incorrect Answer
    C 60 days Correct Answer Incorrect Answer
    D 30 days Correct Answer Incorrect Answer

    Solution

    A + B = 15 days B + C = 20 days Work = L.C.M (15, 20) = 60 A + B = 4 B + C = 3 (A + B) × 3 + (B + C) × 8 + 12C = 60 4 × 3 + 3 × 8 + 12C = 60 12 + 24 + 12C = 60 12C = 60 – 36 12 C = 24 C = 2 Now, B + C = 3 B + 2 = 3 B = 1 ∴ B takes = 60/1 = 60 days