Question
A and B together can do a piece of work in 15 days which B and C together can do in 20 days. After A has been working at it for 3 days and then by B for 11 days & then C finishes it in 20 days. In how many days B could finish the work?
More Time and work Questions
- ‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.1400, then fin...
- 30 labourers are assigned to dig a 4 km canal. After 12 days, only half of the work is over. Later, 6 more labourers are added. Find in how many days the r...
- 15 men can finish a job in 24 days, while 36 women can do the same job in 20 days. How long will 1 man and 1 woman take to complete the work together?
- ‘A’ and ‘B’ together can complete a work in 12 days, while ‘B’ and ‘C’ together can complete the work in 8 ...
- A and B can complete a piece of work in 12 days and 15 days respectively. They start working together, but after 4 days, A leaves. In how many more days wi...
- Leela and Laila, working together, can complete a task in 18 days. Given that Laila is 125% more efficient than Leela, how long would it take for Laila to ...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- 55 men can complete a piece of work in 12 days. 15 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remainin...
- 'Aman' and 'Bittu' alone can do some work in 30 days and 45 days, respectively. They work together for eleven days after which both 'Aman' and 'Bittu' are ...
- 'Pooja' can complete a work in 28 days. She started the work and left after 14 days from starting. The remaining work was done by 'Ritika' in 21 days. Find...