Question
A and B together can do a piece of work in 15 days which
B and C together can do in 20 days. After A has been working at it for 3 days and then by B for 11 days & then C finishes it in 20 days. In how many days B could finish the work?Solution
A + B = 15 days B + C = 20 days Work = L.C.M (15, 20) = 60 A + B = 4 B + C = 3 (A + B) × 3 + (B + C) × 8 + 12C = 60 4 × 3 + 3 × 8 + 12C = 60 12 + 24 + 12C = 60 12C = 60 – 36 12 C = 24 C = 2 Now, B + C = 3 B + 2 = 3 B = 1 ∴ B takes = 60/1 = 60 days
Match the following inventions with it’s Inventors.
A. Microscope                     1. D.G. Fahrenheit
B. Thermo...
Which of the following are functions of the endocrine system?
1. Regulation of metabolism through hormones like thyroid hormone.
2. Regula...
In which Indian state is Kamlang Wildlife Sanctuary and Tiger Reserve located?
In which state is the Nanda Devi Fair primarily celebrated?
Who received the Nobel Prize for Physiology or Medicine for the year 2020?
Next QUAD Summit 2023 will be held at which place?
'Indian Home Rule Society' was established in -
Match the following:
Nahar Wildlife Sanctuary is located in which state of India?
Where in India is the headquarters of Citibank India located?