      Question

      Working in a shift of 5 hours 39 workers take 12 days to

      build a stretch of highway. In how many days will 30 workers working 6 hours a day, complete the work?
      A 13 days Correct Answer Incorrect Answer
      B 30 days Correct Answer Incorrect Answer
      C 45 days Correct Answer Incorrect Answer
      D 28 days Correct Answer Incorrect Answer

      Solution

      => M1 ├Ч H1 ├Ч D1 = M2 ├Ч H2 ├Ч D2

      => 39 ├Ч 12 ├Ч 5 = 30 ├Ч 6 ├Ч D2

      => D2 = 13 days