Working in a shift of 5 hours 39 workers take 12 days to build a stretch of highway. In how many days will 30 workers working 6 hours a day, complete the work?
=> M1 × H1 × D1 = M2 × H2 × D2
=> 39 × 12 × 5 = 30 × 6 × D2
=> D2 = 13 days
Market failure is the inability of
When a firm’s decision to produce decreases the wellbeing of others, but the firm does not compensate those others. It is a case of______.
...Assume that there are equal numbers of male and female students in a university. Of all male students, 10 per cent major in economics; and of ...
Which of the following statements about contingent valuation is correct?
GNP exceeds NNP by:
Hedonic pricing is a method used for environmental valuation that:
Law of diminishing returns only applies to cases where
Which of the following statements is associated with general equilibrium analysis?
Individuals can now directly purchase treasury bills, dated securities, sovereign gold bonds (SGB) and state development loans (SDLs) under RBI’s ___...
If the currency-deposit ratio equals 0.5 and the reserve-deposit ratio equals 0.1, then the money multiplier is