📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      Working in a shift of 5 hours 39 workers take 12 days to

      build a stretch of highway. In how many days will 30 workers working 6 hours a day, complete the work?
      A 13 days Correct Answer Incorrect Answer
      B 30 days Correct Answer Incorrect Answer
      C 45 days Correct Answer Incorrect Answer
      D 28 days Correct Answer Incorrect Answer

      Solution

      => M1 × H1 × D1 = M2 × H2 × D2

      => 39 × 12 × 5 = 30 × 6 × D2

      => D2 = 13 days

      Practice Next
      ask-question