Question
A can complete a piece of work in 20 days, and B in 30 days. They work together for 6 days, after which A leaves. In how many more days will B finish the remaining work?
More Time and work Questions
- A and B can complete a task together in 8 days, while B alone takes 16 days to finish it. A began working alone and left after ‘x’ days, after which B comp...
- Alice can build one section of a wooden fence with a base length of 18 meter and a height of 25 meter in 18 days. Bob can construct 80% of one side of a wo...
- X, Y and Z can do a piece of work in 90 days, 40 days and 120 days respectively. If they all work together alternatively starting with X, Y than Z respecti...
- A’ and ‘B’ alone can do a certain work in 20 days and 30 days, respectively. Both started the work together but after ‘x’ days ‘A’ left the work and the re...
- 'M' alone finishes a project in 30 days. 'M' and 'N' together can complete the same project in 16(2/3) days. How many days would 'N' need to do the project...
- P’s 4 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 40% of the wor...
- Anand is capable of finishing a task in 36 days when working solo. Akash, being 40% more efficient than Anand, can accomplish tasks quicker. Calculate how ...
- Two efficient workers or three non-efficient workers can complete a certain task in 20 days. If each efficient worker improves their efficiency by 33(1/3)%...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 25 days, respectively. They started working together but ‘A’ left after 4 days. Find the time taken by ‘B...
- A and B together can complete a work in 12 days, B and C together in 16 days, and A and C together in 24 days. All three start working together. After 3 da...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)