Question
A can complete a piece of work in 20 days, and B in 30 days. They work together for 6 days, after which A leaves. In how many more days will B finish the remaining work?
Solution
ATQ,
Aβs 1 day work = 1/20, Bβs = 1/30 Together 1 day = (1/20 + 1/30) = 1/12 Work done in 6 days = 6/12 = Β½ Remaining = Β½ B alone = (Β½) Γ· (1/30) = 15 days
More Time and work Questions
- P and Q can do a piece of work in 32 and 40 days respectively. They began to work together but P leaves after sometimes and Q completed remaining work in 1...
- A and B together can finish a work in 10 days. If A alone can finish it in 25 days, in how many days can B alone finish it?
- P and Q together can do a piece of work in 30 days, Q and R together can do it in 20 days. P starts the work and works on it for 5 days, then Q takes it up...
- A can fabricate a divider in 15 days , while B alone can assemble it in 25 days, If they construct it together and get an installment of Rs 7000, then find...
- A can finish a work in 12 days and B can finish the same work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alon...
- A can complete a piece of work in 10 days and B can complete it in 15 days. They start working together, but B leaves after 3 days. In how many more days w...
- The time taken by βAβ to build a wall alone is 50% more than the time taken by him to build it along with βBβ. βBβ will take how much percent more time to ...
- 10 men or 50 women can complete a piece of work in 40 days. A man and a woman together complete the work and receive a total wage of Rs. 6,000. Find the di...
- A can complete a piece of work in 18 days. B can complete the same work in 72 days. While C is 33(1/3)Β more efficient than B. All three started working to...
- Sudhanshu completes `1/3` of work in 12 days, then he completes the remaining work with the help of Neeraj in 4 days. The time required for Neer...