Question
A can complete a piece of work in 20 days, and B in 30
days. They work together for 6 days, after which A leaves. In how many more days will B finish the remaining work?Solution
ATQ,
A’s 1 day work = 1/20, B’s = 1/30 Together 1 day = (1/20 + 1/30) = 1/12 Work done in 6 days = 6/12 = ½ Remaining = ½ B alone = (½) ÷ (1/30) = 15 days
(749.98% of 639.897) ÷ 23.97 = ?2 - 279.98% of 19.99
The equation of a hyperbola whose conjugate axis equals its transverse axis is:
69 73 64 80 ? 91
In a cyclic quadrilateral ABCD, angle A = 70 degrees and angle B = 100 degrees. What is the measure of angle C?
A bag contains red, blue, and green balls in the ratio of 2:4:5. If two balls are randomly selected from the bag, the probability that both are blue is ...
The ratio of the incomes of Vineet and Vidya is 5:2 respectively. Vineet saves 30% of his income while Vidya saves 20% of his income. The sum of their e...
If (a + b) = 8 and ab = 10, then find the value of (a2 + b2).
A tank is filled with 3 inlet pipes and 2 outlet pipes. Inlet pipes A, B, and C can fill the tank in 6 hours, 8 hours, and 12 hours, respectively. Outle...