      A can complete a piece of work in 20 days, and B in 30

      days. They work together for 6 days, after which A leaves. In how many more days will B finish the remaining work?
      A 15 days Correct Answer Incorrect Answer
      B 10 days Correct Answer Incorrect Answer
      C 17 days Correct Answer Incorrect Answer
      D 33 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      A’s 1 day work = 1/20, B’s = 1/30 Together 1 day = (1/20 + 1/30) = 1/12 Work done in 6 days = 6/12 = ½ Remaining = ½ B alone = (½) ÷ (1/30) = 15 days