Question
A can complete a piece of work in 20 days, and B in 30 days. They work together for 6 days, after which A leaves. In how many more days will B finish the remaining work?
More Time and work Questions
- A’ and ‘B’ together can complete a work in 15 days while ‘A’ takes 20 days to complete the same work alone. If ‘C’ is 50% more efficient than ‘B’, then fin...
- 25 men can complete a piece of work in 30 days. ‘x’ men started the work and after 24 days 60 more men joined them so that whole work was finished in the d...
- 132 unit of work can be completed by P alone in 22 days. P started working alone and joined by Q after 10 days such that they completed the remaining work ...
- Twenty laborers can complete a piece of work in 12 days. If 20 laborers started working and after 3 more days, additional laborers joined to complete the r...
- A buffalo alone can plough field ‘A’ in 20 days. A Bull alone can plough the field ‘A’ in 10 days. Find the number of days taken by 1 bulls and 4 buffalo t...
- Aman can finish a task in 9 days while Rohan can finish it in 18 days. They together earn Rs. 27,000 for the task. What is Rohan’s share?
- 15 people can paint a house in 5 days using 15 paintbrushes. In how many days can 10 people paint the same house using p paintbrushes?
- 2 men and 4 boys can together complete a work in 6 days. 3 men and 1 boy can together complete the same work in 5 days. Find the time taken by 10 boys toge...
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- Amit and Anaya can complete a task together in 20 days. If Anaya is 150% more efficient than Amit, how many days will Anaya alone take to finish the task?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt