    Question

    A and B together can complete a piece of work in 8 days.

    B and C together can also complete it in 8 days, while A and C together can complete it in 6 days. In how many days can B alone complete the work?
    A 33 days Correct Answer Incorrect Answer
    B 24 days Correct Answer Incorrect Answer
    C 12 days Correct Answer Incorrect Answer
    D 42 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Let the work done per day by A, B, C be a, b, c respectively. A + B = 1/8 …(i) B + C = 1/8 …(ii) A + C = 1/6 …(iii) Add (i), (ii), (iii): (A + B) + (B + C) + (A + C) = 1/8 + 1/8 + 1/6 2(A + B + C) = 1/4 + 1/6 1/4 + 1/6 = (3/12 + 2/12) = 5/12 So 2(A + B + C) = 5/12 β‡’ A + B + C = 5/24 Now b = (A + B + C) βˆ’ (A + C) = 5/24 βˆ’ 1/6 1/6 = 4/24 So b = 5/24 βˆ’ 4/24 = 1/24 Therefore B alone takes 24 days to complete the work.