πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      The ratio of the efficiency of A, B and C is 3:4:5, if they

      can complete a work in 18 days then A can complete 60% of the work in how many days?
      A 45.5 Correct Answer Incorrect Answer
      B 43.2 Correct Answer Incorrect Answer
      C 48 Correct Answer Incorrect Answer
      D 52 Correct Answer Incorrect Answer

      Solution

      Total work = 12 Γ— 18
      Time taken by A to complete 60% of the work = (12 x 18 x 60)/(3 x 100) = 43.2 days

      Practice Next

      Relevant for Exams:

      ask-question