ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    The ratio of the efficiency of A, B and C is 3:4:5, if they

    can complete a work in 18 days then A can complete 60% of the work in how many days?
    A 45.5 Correct Answer Incorrect Answer
    B 43.2 Correct Answer Incorrect Answer
    C 48 Correct Answer Incorrect Answer
    D 52 Correct Answer Incorrect Answer

    Solution

    Total work = 12 ├Ч 18
    Time taken by A to complete 60% of the work = (12 x 18 x 60)/(3 x 100) = 43.2 days

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question