Question
P can do a piece of work in 15 days, Q can complete
double the work in 30 days and R can do the work in 25 days. If all of them together earn Rs. 2600, then find the money received by Q.Solution
Time taken by P = 15 days Time taken by Q = 15 days Time taken by R = 30 days Let the total work be 75 units. P’s one day work = 5 units Q’s one day work = 5 units R’s one day work = 3 units Amount received by Q = 2600 × (5/13) = Rs. 1000
Which team won the Women's Asia Cup title in 2024?
What technological advancement was achieved by AFMS and IIT Kanpur through their collaboration?
How much did China invest in the world's largest hydropower dam on the Brahmaputra River?
India, _________, the UK and Small Island Developing States (SIDS) will be launching a new initiate for Infrastructure for Resilient Island States (IRIS).
Which of the following statements regarding the Neem Summit & Global Neem Trade fair is/are correct?
1. The Summit is organized in collaboration ...
Which of the following statements is correct regarding the Project Swasthya Nagaram launched in Telangana for TB-Free Municipalities?
Ibrahim Boubacar Keita passed away recently. He belonged to _______.
Where was the “Indian Mango Mania 2025” campaign launched to promote Indian mangoes?
India’s overall inflation rate is lower than South Africa and Russia, two key emerging market peers in the BRICS grouping of nations.Which country has...
Which bank has entered into a strategic partnership with Manipal Global Education Services, a leading provider of education and learning solutions aimin...