Question

P can do a piece of work in 15 days, Q can complete double the work in 60 days and R can do the work in 40 days. If all of them together earn Rs. 3000, then find the money received by Q.

A Rs.1000
B Rs.800
C Rs.1200
D Rs.900
E None of these