    • Question

      A task can be done by ‘p’ men in 32 days. If the team

      had 8 more men, the work would finish in 24 days. Find the value of ‘p’.
      A 50 Correct Answer Incorrect Answer
      B 75 Correct Answer Incorrect Answer
      C 24 Correct Answer Incorrect Answer
      D 95 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Total work = 32p units

      So, 32p = (p + 8) × 24

      Or, 32p – 24p = 192

      Or, 8p = 192

      Therefore, p = 192 / 8 = 24