Question
A, B and C can complete a work as follows, (A +
- B in 12 days, (B +
- C in 15 days, and (A +
- C in 20 days. In how many days can A alone complete the work?
More Time and work Questions
- A can finish a job in 20 days while B can finish same job in 30 days. A and B both worked for 5 days and C joins them. In next 3.5 days, all three have man...
- 'Sunil', 'Arjun', and 'Rahul' can complete a task individually in 45, 60, and 90 days respectively. All began the work together, but Sunil and Arjun left 1...
- Two people, A and B, working separately can sanitize a building in 6 and 10 hours, respectively. They work in stretches of one hour alternately. If A begin...
- A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio of the ef...
- ‘A’ and ‘B’ can do a piece of work in 22 days and 25 days, respectively. If they started the work together and worked on it for 6 days, then find the time ...
- 126 unit of work can be completed by P alone in 21 days. P started working alone and joined by Q after 10 days such that they completed the remaining work ...
- Rahul can complete a project in 50 days, while Karan can finish the same project in 75 days. Rahul starts working alone, and after 30 days, Karan joins him...
- Question 8
- Anjali,' 'Bheem,' and 'Chetna' started a business together with initial investments of Rs. 3,875, Rs. (B + 2700), and Rs. 'B,' respectively. After 16 month...
- P’s 4 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 40% of the wor...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)