Question
Working 6 hours a day, Rahul can complete a work in 25
days. How many hours a day should he work to complete the same work in 15 days?Solution
ATQ,
Let the efficiency of Rahul be 'x' units per hour
Therefore, total work = 6 Ă— 25 Ă— x = 150x units
Let the time he should work to complete the work in 15 days be 'y' hours a day.
ATQ;
150x = 15 Ă— y Ă— x
Or, y = 10
Therefore, he should work for 10 hours a day.
Alternate solution:
Required time = (6 Ă— 25) Ă· 15 = 10 hours
Who is credited with introducing Local Self Government in India?
Which of the following best describes the Raman Effect?
Who were the awardees in Physical Sciences (Shanti Swaroop Bhatnagar Prize) for the year 2022?
How much did foreign direct equity (FDI) investments contract by in the calendar year 2023, according to Department for Promotion of Industry and Intern...
“Dudhwa Tiger Reserve” is a part of National Park in which part of India?
Which of the following statements is incorrect about Democracy?
Union Minister Nitin Gadkari has launched the Rs 5600 crore National Highway project in which state?
Who was recently appointed as the Chairman of the Asian Cricket Council (ACC) during their virtual Annual General Meeting?
Consider the statements about Kapdaganda shawl:
1. Recently it bagged the Geographical Indication (GI) tag.
2. This GI tag is valid for 10...
In India handed over the MK-3 ALH helicopter built by Hindustan Aeronautics Limited (HAL) to which country?