Let the efficiency of Neha be 'x' units per hour
Therefore, total work = 5 × 40 × x = 200x units
Let the time she should work to complete the work in 25 days be 'y' hours a day.
ATQ;
200x = 25 × y × x
Or, y = 8
Therefore, she should work for 8 hours a day.
Alternate solution:
Required time = (5 × 40) ÷ 25 = 8 hours
In India, which of the following bills CANNOT be introduced in the Rajya Sabha?
Sarus Crane, recently seen in the news, is the official bird of which state?
In which year was the first Economic Census carried out in India?
What event does the Reserve Bank of India celebrate on 1st April?
A train of length 400 m takes 15 seconds to cross a train of length 300 m travelling at 60 km per hour from the opposite direction along a parallel tra...
Chandrayaan-1 was the first Indian lunar probe under the Chandrayaan programme. Which year was Chandrayaan-1 launched?
In July 2024, Avinash Sable broke the 3000m steeplechase national record at the Paris Diamond League. The steeplechase event includes fixed barriers __...
Who is the most valuable personality according to Kroll’s latest celebrity brand valuation?
Which of the following is added in the national income to obtain personal income of the households?
Find the odd one out