Question
If Neha can complete a work in 40 days by working 5 hours a
day, how many hours per day should she work to complete the same work in 25 days?Solution
ATQ,
Let the efficiency of Neha be 'x' units per hour
Therefore, total work = 5 × 40 × x = 200x units
Let the time she should work to complete the work in 25 days be 'y' hours a day.
ATQ;
200x = 25 × y × x
Or, y = 8
Therefore, she should work for 8 hours a day.
Alternate solution:
Required time = (5 × 40) ÷ 25 = 8 hours
According to the India State Forest Report 2021, which state has shown the highest increase in forest cover?
International labour organization convention 177 was recently seen in the news, is related to?
A shopkeeper sold a laptop after giving two successive discounts of 20% and 5% while making a profit of 30%. Find the approximate...
Auditors use ______ to gather information and determine if they need to conduct substantive testing. Sometimes, they can use analytical methods alone t...
Consider the following statements :
1. Falkland Islands are situated in Pacific Ocean.
2. Red Sea separates Sudan from Egypt.
Ratio of the work done by P, Q and R in one day is 4:2:5 respectively. They all together can complete the work in 35 days. Q and R worked on it for 23 d...
Goods returned by customer will be debited to which account?
How many lines other than those shown in the figure are required to join each corner with another?
Which of the following numbers is divisible by 4?
Which of the following statements is/are incorrect in regards to Green development?
1.At the UNFCCC COP27, Shri Narendra Modi announced Mission L...