Question
40 men or 50 women can build a wall in 30 days. If 40 men and 50 women work together, how many days will they take to complete 60% of the work?
More Time and work Questions
- ‘A’ and ‘B’ can do a piece of work in 30 days and 40 days, respectively. They started working together but ‘A’ left after 9 days. Find the time taken by ‘B...
- Pipes 'P' and 'Q' can fill a tank in 36 minutes and 72 minutes respectively. A third pipe 'R' can empty it in 1 hour 48 minutes. 'P' and 'R' are turned on ...
- X can do a piece of work in 25 days. He worked at it for 5 days and then Y finished it in 24 days. In how many days can X and Y together finish the work?
- Komal and Seema individually can complete a task in ‘4a’ hours and ‘8a’ hours respectively. If they together can complete half of the work in 8 hours, then...
- The ratio of time taken by P, Q and R to complete work alone is 4:5:2 respectively. If all three together complete the work in 8 days, then find in how man...
- ‘A’ can do a piece of work in 12 days. ‘B’ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.1540, then fin...
- Naina and Kalpana working together can do a piece of work in 10 days, whereas Naina alone can do it in 12 days. In how many days can Kalpana do it alone?
- Karan is five times as efficient as Varun and twice as efficient as Arjun. If Varun takes 30 days to finish some work, then find the time taken by Karan an...
- X, Y, and Z alone can complete a language translation in 60, 90, and 36 days respectively. They started working together, but after 5 days, Z left the job,...
- ‘P’ and ‘Q’ can complete a task together in 30 days. If ‘P’ is 60% more efficient than ‘Q’, how many days will ‘Q’ take to finish the work alone?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt