ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    тАШPтАЩ is 25% more efficient than тАШQтАЩ. тАШQтАЩ

    worked alone for 6 days and then тАШPтАЩ finished the rest of the work in 4 days. How many days would тАШQтАЩ alone take to complete the entire work?
    A 21 days Correct Answer Incorrect Answer
    B 13 days Correct Answer Incorrect Answer
    C 11 days Correct Answer Incorrect Answer
    D 27 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let efficiency of Q = 8x units/day Then efficiency of P = 8x ├Ч 1.25 = 10x units/day Work done by Q in 6 days = 8x ├Ч 6 = 48x units Work done by P in 4 days = 10x ├Ч 4 = 40x units Total work = 48x + 40x = 88x units Time taken by Q alone to complete the whole work = 88x / 8x = 11 days

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question