Question
‘P’ is 25% more efficient than ‘Q’. ‘Q’
worked alone for 6 days and then ‘P’ finished the rest of the work in 4 days. How many days would ‘Q’ alone take to complete the entire work?Solution
ATQ,
Let efficiency of Q = 8x units/day Then efficiency of P = 8x × 1.25 = 10x units/day Work done by Q in 6 days = 8x × 6 = 48x units Work done by P in 4 days = 10x × 4 = 40x units Total work = 48x + 40x = 88x units Time taken by Q alone to complete the whole work = 88x / 8x = 11 days
169, 224, 293, 385, 497, 629
Find the wrong number in the given number series.
20, 33, 50, 69, 93, 121
25Â Â Â 26Â Â Â Â 28Â Â Â Â 32Â Â Â Â 42Â Â Â Â 56
Find the wrong number in the given number series.
8, 12, 23, 40, 66, 103
8137, 5405, 3669, 2701, 2201, 1997
Find the wrong number in the given number series.
78, 66, 51, 39, 20, 12
2824Â Â Â Â 2314Â Â Â Â Â 1973Â Â Â Â 1759Â Â Â Â 1634Â Â Â Â 1574
In each of the following number series, one term is wrong. Find the wrong term.
3, 7, 13, 21, 31, 42, 57
Find the wrong term in the given series below.
2847, 2954, 2799, 3088, 2727, 3256
Find the wrong number in the given number series.
2, 5, 10, 17, 26, 38, 50